# Foremost Paving, INC.: TxDOT rehabilitation of existing road contract 81% complete, FM 755, Starr County ($26,073,604, 4 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Foremost Paving, INC. |
| Subcontractors | Highway Barricades And Services, LLC (3.01%); Soil Tech Advance INC. (1.09%); Texas Highway Systems, INC. (0.68%); *austin Traffic Signal Construction Co., INC. (0.02%) |
| Progress | 81.15% complete, 90.58% of time used |
| Amount | $26,073,604 revised (original $24,639,662) |
| Change orders | $29,265 |
| Paid to date | $20,018,771 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 755, FM 1017 to FM 2294, Starr County, Pharr District |
| Let / began | 2024-07-10 / 2024-10-03 |
| Latest estimate | 2026-10-02 |
| Contract number | 7243203 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.