# Foremost Paving, INC.: TxDOT rehabilitation of existing road contract 100%+ complete, FM 510, Cameron County ($16,526,690, 6 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Foremost Paving, INC. |
| Subcontractors | Soil-Tech, INC. (0%); Highway Barricades And Services, LLC (2.45%); Laredo Striping, INC. (2.01%); Texas Highway Systems, INC. (0.47%); Rio Grande Rebar Rodbusters, LLC (0.01%); Soil Tech Advance INC. (2.45%) |
| Progress | 102.83% complete, 93.67% of time used |
| Amount | $16,526,690 revised (original $15,675,731) |
| Change orders | $479,959 |
| Paid to date | $16,612,739 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 510, FM 3462 to FM 1847, Cameron County, Pharr District |
| Let / began | 2023-08-03 / 2024-02-05 |
| Latest estimate | 2026-10-01 |
| Contract number | 8233210 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.