# Foremost Paving, INC.: TxDOT new location freeway contract 43% complete, US 77, Kenedy County ($34,389,236, 8 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Foremost Paving, INC. |
| Subcontractors | Highway Barricades And Services, LLC (0.54%); Rio Grande Rebar Rodbusters, LLC (0.01%); Southwest Road & Safety Contractors, LTD. (1.26%); Gp7 Construction INC. (0.4%); Long Legacy Enterprises, LLC (0.14%); Texas Icon Construction, LLC (2.26%); D&G Energy Corporation (0.78%); Texas Highway Systems, INC. (0.25%) |
| Progress | 42.54% complete, 85.65% of time used |
| Amount | $34,389,236 revised (original $33,508,386) |
| Paid to date | $14,253,549 |
| Work | New Location Freeway |
| Location | US 77, 9.6 MILES NORTH OF NORIAS RD to NORIAS RD., Kenedy County, Pharr District |
| Let / began | 2024-08-01 |
| Latest estimate | 2026-10-01 |
| Contract number | 8243002 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.