# Foremost Paving, INC.: TxDOT new location freeway contract 34% complete, US 77, Kenedy County ($94,446,877, 10 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Foremost Paving, INC. |
| Subcontractors | Rio Grande Rebar Rodbusters, LLC (0.05%); West Texas Rock Resources, LLC (0.02%); D&G Energy Corporation (0.44%); Gp7 Construction INC. (0.97%); Highway Barricades And Services, LLC (0.41%); Texas Highway Systems, INC. (0.14%); Aaron Concrete Contractors, LLC (0.55%); Scott Derr Painting Co, LLC (0.11%); Long Legacy Enterprises, LLC (0.2%); Texas Icon Construction, LLC (2.9%) |
| Progress | 33.77% complete, 56.5% of time used |
| Amount | $94,446,877 revised (original $93,082,027) |
| Paid to date | $31,434,822 |
| Work | New Location Freeway |
| Location | US 77, 6.33 MILES NORTH OF NORIAS RD to 1.46 MILES NORTH OF NORIAS RD, Kenedy County, Pharr District |
| Let / began | 2024-08-02 / 2025-03-26 |
| Latest estimate | 2026-10-01 |
| Contract number | 8243201 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.