# Foutsco Paving Company, LLC: TxDOT rehabilitation of existing road contract 74% complete, US 287, Ellis County ($17,659,925, 3 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Foutsco Paving Company, LLC |
| Subcontractors | Stripe-A-Zone, LLC (0.2%); Linear Traffic Markings LLC (1.8%); Mar-Zap Construction, LLC (0.14%) |
| Progress | 73.54% complete, 56.92% of time used |
| Amount | $17,659,925 revised (original $17,308,925) |
| Paid to date | $12,729,539 |
| Work | Rehabilitation Of Existing Road |
| Location | US 287, BS 287Q to DARTMOOR DRIVE (END OF CS 0172-05), Ellis County, Dallas District |
| Let / began | 2025-10-08 / 2026-03-02 |
| Latest estimate | 2026-10-05 |
| Contract number | 10253033 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.