# Foutsco Paving Company, LLC: TxDOT widen non-freeway contract 100%+ complete, FM 1806, Montague County ($6,550,191, 8 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Foutsco Paving Company, LLC |
| Subcontractors | Linear Traffic Markings LLC (1.28%); Texas Traffic And Barricade, LLC (0.36%); Marcoms Construction LLC (0.72%); Wolfe Construction Group, Incorporated (0.77%); West Texas Rumble Strip LLC (0.17%); Diibs Specialists, LLC (0.95%); Legacy Construction Management Services, LLC (1.53%); W. S. Construction Company (23%) |
| Progress | 109.58% complete, 70.47% of time used |
| Amount | $6,550,191 revised (original $6,384,868) |
| Change orders | $146,523 |
| Paid to date | $7,156,905 |
| Work | Widen Non-Freeway |
| Location | FM 1806, 0.15 MI W OF HILL TOP RD to SH 59, Montague County, Wichita Falls District |
| Let / began | 2025-06-05 / 2025-08-07 |
| Latest estimate | 2026-10-01 |
| Contract number | 6253209 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.