# Foutsco Paving Company, LLC: TxDOT maintenance contract 100%+ complete, IH0820, Tarrant County ($4,301,532)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Foutsco Paving Company, LLC |
| Progress | 110.27% complete, 99.73% of time used |
| Amount | $4,301,532 revised (original $4,210,079) |
| Change orders | $92,558 |
| Paid to date | $4,744,682 |
| Work | Maintenance |
| Location | IH0820, VARIOUS LOCATIONS WITHIN to NORTH TARRANT COUNTY, Tarrant County, Fort Worth District |
| Let / began | 2025-07-01 / 2025-09-22 |
| Latest estimate | 2026-10-01 |
| Contract number | 7254020 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.