# Foutsco Paving Company, LLC: TxDOT restoration contract 100%+ complete, SL 12, Dallas County ($15,309,531, 12 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Foutsco Paving Company, LLC |
| Subcontractors | S & S Bridge Painting, INC. (7.94%); Straight Line Sawing & Sealing, INC. (10.94%); Act Saw Cutting & Removal (1.12%); Fortson Contracting, INC. (7.94%); Macias Specialty Contracting LLC (0.14%); Durable Specialties, INC. (0%); Ibctx, LLC (0.42%); Gibson & Associates, INC. (6.14%); Gregory Pile Driving, INC. (0.37%); Jr West Texas Concrete LLC (2.26%); Linear Traffic Markings LLC (2.76%); Mica Corporation (1.11%) |
| Progress | 100.73% complete, 99.22% of time used |
| Amount | $15,309,531 revised (original $14,715,096) |
| Change orders | $6,134 |
| Paid to date | $14,829,398 |
| Work | Restoration |
| Location | SL 12, SS 244 to IH 30, Dallas County, Dallas District |
| Let / began | 2024-08-02 / 2025-03-05 |
| Latest estimate | 2026-10-02 |
| Contract number | 8243211 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.