# Gibson & Associates, INC.: TxDOT overlay contract 100%+ complete, IH 35, Bexar County ($40,722,716, 14 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | Gibson & Associates, INC. |
| Subcontractors | Serna's Trucking (0%); S & S Bridge Painting, INC. (2.83%); (Inactive)aaron Concrete Contractors, L.P. (0.48%); The Levy Company, INC. (1.8%); Lloyd D. Nabors Demolition LLC (1.04%); Ibctx, LLC (2.56%); Structural Technologies, LLC (0.49%); Pivot Engineers, PLLC (0.03%); Roy Jorgensen Associates, INC. (0.11%); Macias Specialty Contracting LLC (2.34%); Flasher Equipment Company (1.02%); Beck-Reit & Sons, LTD. (0.16%); Austin Bridge & Road Services, LP (20.9%); Diibs Specialists, LLC (0.1%) |
| Progress | 103.43% complete, 95.96% of time used |
| Amount | $40,722,716 revised (original $25,956,303) |
| Change orders | $14,766,413 |
| Paid to date | $42,119,444 |
| Work | Overlay |
| Location | IH 35, LAREDO ST. to AUSTIN ST., Bexar County, San Antonio District |
| Let / began | 2022-10-07 / 2023-05-01 |
| Latest estimate | 2026-10-06 |
| Contract number | 10223203 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.