# Gibson & Associates, INC.: TxDOT maintenance contract 100%+ complete, US 83, Collingsworth County ($7,475,320, 9 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Gibson & Associates, INC. |
| Subcontractors | Nelson Industrial Services, INC. (0.41%); Southeast Grinding And Grooving LLC (0.13%); Dustrol, INC. (0.28%); Alamo Brothers Concrete INC (12.77%); Southwest Road & Safety Contractors, LTD. (1.02%); Macias Specialty Contracting LLC (19.41%); Trp Construction Group, LLC (1.72%); 1 Priority Environmental Services, LLC (0.36%); Ibctx, LLC (6.37%) |
| Progress | 103.48% complete, 98.92% of time used |
| Amount | $7,475,320 revised (original $7,277,550) |
| Change orders | $197,770 |
| Paid to date | $7,735,267 |
| Work | Maintenance |
| Location | US 83, US 83 @ ELM CREEK to 1, Collingsworth County, Childress District |
| Let / began | 2024-10-02 / 2025-05-08 |
| Latest estimate | 2026-10-05 |
| Contract number | 10243221 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.