# Gibson & Associates, INC.: TxDOT maintenance contract 77% complete, SH 19, Delta County ($2,552,727, 10 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Gibson & Associates, INC. |
| Subcontractors | Clear Restoration, LLC (0.99%); Ivs Hydro, INC (3.15%); Nelson Industrial Services, INC. (0.42%); D. L. Lennon Incorporated - Contractor (0.7%); The Truesdell Corporation (20.22%); Dustrol, INC. (1.19%); Emery Sapp & Son's INC. (1.74%); Flex Supply, LLC (0.88%); Striping Technology, L.P. (2.24%); Macias Specialty Contracting LLC (5.71%) |
| Progress | 76.96% complete, 47.51% of time used |
| Amount | $2,552,727 revised (original $2,541,166) |
| Paid to date | $1,955,804 |
| Work | Maintenance |
| Location | SH 19, VA LOCATIONS, Delta County, Paris District |
| Let / began | 2026-01-06 / 2026-04-27 |
| Latest estimate | 2026-10-05 |
| Contract number | 1263021 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.