# Gibson & Associates, INC.: TxDOT rehabilitation of existing road contract 96% complete, IH 35E, Dallas County ($23,771,771, 13 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Gibson & Associates, INC. |
| Subcontractors | Axis Contracting, INC. (3.94%); West Texas Rock Resources, LLC (0.02%); Stoic Civil Construction, INC. (0.19%); Southern Cross Contractors, LLC (3.1%); S & S Bridge Painting, INC. (1.63%); Macias Specialty Contracting LLC (4.07%); Jr West Texas Concrete LLC (7.04%); Global Erosion Control, INC. (0.23%); Fc Traffic Control, INC. (0.21%); Austin Bridge & Road Services, LP (29.62%); Act Saw Cutting & Removal (0.23%); Linear Traffic Markings LLC (0.49%); Superior Traffic Control, LLC (0.05%) |
| Progress | 96.05% complete, 101.75% of time used |
| Amount | $23,771,771 revised (original $22,250,006) |
| Change orders | $596,265 |
| Paid to date | $21,942,784 |
| Work | Rehabilitation Of Existing Road |
| Location | IH 35E, SS 348 to IH 635, Dallas County, Dallas District |
| Let / began | 2024-09-06 / 2025-03-04 |
| Latest estimate | 2026-10-02 |
| Contract number | 9243206 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.