# Gilvin-Terrill, LTD.: TxDOT rehabilitation of existing road contract 69% complete, SH 194, Hale County ($26,804,100, 6 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Gilvin-Terrill, LTD. |
| Subcontractors | Fusion Communications, LLC (0.65%); Trp Construction Group, LLC (1.03%); Dk Contracting, LLC (0.36%); Alamo Brothers Concrete INC (6.53%); Artex Electric, INC. (11.16%); Lmse Trucking, LLC (0.72%) |
| Progress | 68.65% complete, 72.13% of time used |
| Amount | $26,804,100 revised (original $26,114,007) |
| Paid to date | $17,927,385 |
| Work | Rehabilitation Of Existing Road |
| Location | SH 194, IH 27 to FM 3466, Hale County, Lubbock District |
| Let / began | 2024-10-01 / 2025-03-31 |
| Latest estimate | 2026-10-06 |
| Contract number | 10243004 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.