# Gilvin-Terrill, LTD.: TxDOT hazard elimination & safety contract 62% complete, BI 40D, Potter County ($31,189,683, 11 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Gilvin-Terrill, LTD. |
| Subcontractors | Dustin Allen, INC. (0.15%); Fc Traffic Control, INC. (0.1%); Garza Concrete Construction (1.98%); Lmse Trucking, LLC (0.45%); Scr Civil Construction, LLC (2.18%); Trp Construction Group, LLC (1.16%); Vaca Underground Utilities INC (4.34%); Wolfe Construction Group, Incorporated (0.24%); W. S. Construction Company (6.7%); Alamo Brothers Concrete INC (14.59%); Marcoms Construction LLC (0.21%) |
| Progress | 62.11% complete, 98.12% of time used |
| Amount | $31,189,683 revised (original $30,982,054) |
| Change orders | $197,629 |
| Paid to date | $19,367,022 |
| Work | Hazard Elimination & Safety |
| Location | BI 40D, IH 40 to SL 279, Potter County, Amarillo District |
| Let / began | 2024-10-02 / 2025-01-20 |
| Latest estimate | 2026-10-06 |
| Contract number | 10243203 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.