# Gilvin-Terrill, LTD.: TxDOT widen non-freeway contract 100%+ complete, FM 57, Fisher County ($4,292,315, 8 subs)

**Score:** 60/100

| Field | Value |
|---|---|
| Prime contractor | Gilvin-Terrill, LTD. |
| Subcontractors | Hjc Farms, INC. (1.28%); Duke Electric Co., INC. (3.1%); Black Jack Energy Services, LLC (24.82%); Flat Line, INC. (2.25%); Murray Construction (1.53%); Dustrol, INC. (0.31%); Texas Environmental Management - San Antonio, INC. (4.09%); H & F Trucking (0.51%) |
| Progress | 101.74% complete, 171.08% of time used |
| Amount | $4,292,315 revised (original $3,763,383) |
| Change orders | $525,931 |
| Paid to date | $4,363,876 |
| Work | Widen Non-Freeway |
| Location | FM 57, SH 70 to PLUMB CREEK, Fisher County, Abilene District |
| Let / began | 2024-03-05 / 2024-07-22 |
| Latest estimate | 2026-10-06 |
| Contract number | 3243021 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.