# Gilvin-Terrill, LTD.: TxDOT bridge widening or rehabilitation contract 100%+ complete, IH 27, Swisher County ($4,001,674, 7 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Gilvin-Terrill, LTD. |
| Subcontractors | Alamo Brothers Concrete INC (0%); Dustrol, INC. (0%); S&S Bridge Painting (0%); Texop Construction (0%); Structural Integrity Group LLC (11.99%); Gibson & Associates, INC. (15.3%); Trp Construction Group, LLC (4.24%) |
| Progress | 114.43% complete, 116.67% of time used |
| Amount | $4,001,674 revised (original $3,742,466) |
| Change orders | $156,209 |
| Paid to date | $4,461,190 |
| Work | Bridge Widening Or Rehabilitation |
| Location | IH 27, ON FM 1881 to AT ATSF RAILROAD, Swisher County, Lubbock District |
| Let / began | 2021-05-06 / 2021-09-13 |
| Latest estimate | 2026-10-06 |
| Contract number | 5213215 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.