# Granite Construction Company: TxDOT miscellaneous construction contract 100%+ complete, SH 288, Brazoria County ($39,055,799, 28 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Granite Construction Company |
| Subcontractors | Hb Farmer Foundation, LLC (2.14%); C.G. Anthony Deliveries, LLC (0.37%); Dustrol, INC. (3.8%); Professional Traffic Control LLC (0.31%); Jrb Engineering, LLC (0.15%); Republic Traffic Safety, INC. (0.41%); Quality Turf Farms, L.C. (1.86%); Milstead Highway Services, LLC (0.55%); Antigo Construction, INC. (0.1%); James Construction Group, LLC (5.47%); Sb Fleet - Lube, LLC (0.22%); A&J Rebar LLC (0.58%); Creacom, INC. (1.21%); Aaron Concrete Contractors, LLC (1.08%); Vulcan Materials Asphalt And Construction, LLC (5.47%); Yellowstone Landscape - Central, INC. (0.04%); Willow City Sign & Rail, INC. (0.1%); Clean-Co Systems, INC. (0.05%); Scott Derr Painting Co, LLC (0.16%); Forde Construction Company, INC. (0.27%); Allstate Signal & Construction, LLC (0.32%); Doran Steel, INC. (0.13%); Primate Construction, LP (0.2%); Romar Unlimited, INC. (0.81%); Curb Planet INC. (0.02%); Roadway Specialties, INC. (0.3%); Sk Concrete Services LLC (0.12%); (Inactive)royal Rebar (0.12%) |
| Progress | 102.84% complete, 96.09% of time used |
| Amount | $39,055,799 revised (original $38,504,600) |
| Change orders | $451,167 |
| Paid to date | $40,061,699 |
| Work | Miscellaneous Construction |
| Location | SH 288, AT CR 48 to ., Brazoria County, Houston District |
| Let / began | 2022-06-29 / 2022-11-08 |
| Latest estimate | 2026-09-30 |
| Contract number | 6223404 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.