# Granite Construction Company: TxDOT new location freeway contract 96% complete, US 175, Kaufman County ($57,895,683, 28 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Granite Construction Company |
| Subcontractors | (Inactive)royal Rebar (0.07%); Stripe-A-Zone, LLC (0.59%); Fc Traffic Control, INC. (0.01%); Dallas Lite And Barricade, INC. (0.06%); Q. Roberts Trucking Incorporated (8.81%); Cowboy Trucking (0.7%); Toro Bravo Construction, LLC (0.03%); USA Swppp Inspections, INC. (0.26%); A Brothers Milling, LLC (0.26%); Primate Construction, LP (0.06%); Midway Striping & Sealcoating (0.01%); Dustrol, INC. (0.02%); Stewart Ranch Services LLC (0.03%); Peachtree Construction, LTD. (12.03%); Fortson Contracting, INC. (0.27%); Traffic Highway Maintenance, LLC (0.59%); Wylie Drilling & Drainage, INC. (0.64%); Alpha Testing, INC. (0.06%); Next Generation Construction & Environmental, LLC (0.05%); Texas Environmental Management - San Antonio, INC. (0.65%); J.H. Painting Company (0.12%); Dfw Rebar, INC. (0%); Tex Op Construction, LP (0.01%); Road Solutions L.L.C. (0.9%); Circle H Boring, LLC (0.13%); Aaron Concrete Contractors, LLC (0.75%); West Texas Rock Resources, LLC (0.02%); Aaa Drilling Foundation Company, INC. (0.02%) |
| Progress | 96.09% complete, 99.25% of time used |
| Amount | $57,895,683 revised (original $56,899,999) |
| Change orders | $588,284 |
| Paid to date | $55,240,373 |
| Work | New Location Freeway |
| Location | US 175, WEST OF FM 148 BYPASS to EAST OF FM 148 BYPASS, Kaufman County, Dallas District |
| Let / began | 2023-06-27 / 2023-10-01 |
| Latest estimate | 2026-10-02 |
| Contract number | 6233405 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.