# Grey Sky Construction LLC: TxDOT traffic signal contract 62% complete, IH 45, Ellis County ($8,665,898, 4 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Grey Sky Construction LLC |
| Subcontractors | Diibs Specialists, LLC (0.03%); Urbanglow Contracting LLC (3.97%); Fnh Construction, LLC (6%); Keller North America, INC. (14.51%) |
| Progress | 62.48% complete, 109.87% of time used |
| Amount | $8,665,898 revised (original $8,081,166) |
| Change orders | $182,733 |
| Paid to date | $5,163,526 |
| Work | Traffic Signal |
| Location | IH 45, AT SH 34 (ENNIS AVENUE) to N/A, Ellis County, Dallas District |
| Let / began | 2025-03-04 / 2025-08-04 |
| Latest estimate | 2026-10-02 |
| Contract number | 3253009 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.