# H. H. Howard & Sons, INC.: TxDOT rehabilitation of existing road contract 82% complete, FM 21, Franklin County ($9,489,385, 9 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | H. H. Howard & Sons, INC. |
| Subcontractors | Bahena Construction Co., INC. (8.56%); Withers Construction, LLC (4.89%); Panola Sign & Barricade, INC. (0.48%); Richard Drake Construction Company, L.P. (10.37%); Striping Technology, L.P. (1.85%); Texop Construction (2.17%); J. H. Oden Contracting Company (2.43%); Morris County Contractors, L.L.C. (0.71%); Southwest Environment Services LLC (1.37%) |
| Progress | 81.63% complete, 72.43% of time used |
| Amount | $9,489,385 revised (original $9,113,599) |
| Paid to date | $7,439,424 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 21, FM 21 FROM SH 37 TO TITUS COUNTY LINE, Franklin County, Paris District |
| Let / began | 2025-04-03 / 2025-05-29 |
| Latest estimate | 2026-10-05 |
| Contract number | 4253007 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.