# Harper Brothers Construction LLC: TxDOT widen freeway contract 86% complete, FM 471, Bexar County ($55,372,256, 21 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Harper Brothers Construction LLC |
| Subcontractors | Curb Planet INC. (0%); Monarch Fence LLC (0.08%); A K Fuquay Construction (2.43%); E-Z Bel Construction, LLC (0.69%); Scott Derr Painting Co, LLC (0.02%); R3 Concrete, LLC (0%); Jag Public Safety, LLC (0.07%); Roadway Specialties, INC. (0.78%); Interstate Barricades & Markings, INC. (0.76%); Flasher Equipment Company (0.4%); Performance Equipment Service (0.22%); Jb Pinnacle Group, LLC (0.09%); Primate Construction, LP (0.01%); Keller North America, INC. (0.44%); Stellar Constructors, LLC (1.81%); Texas Materials Group, INC. (13.26%); Badeco, INC. (6.7%); Adcock 4 Investments, LLC (5.15%); Saeco Electric & Utility, LTD. (2.94%); C-3 Land Clearing, LLC (0.05%); Texas Erosion Control Services (1.11%) |
| Progress | 86.25% complete, 76.42% of time used |
| Amount | $55,372,256 revised (original $49,119,270) |
| Change orders | $6,252,986 |
| Paid to date | $47,756,991 |
| Work | Widen Freeway |
| Location | FM 471, OLD FM 471 to MEDINA COUNTY LINE, Bexar County, San Antonio District |
| Let / began | 2021-12-02 / 2022-04-20 |
| Latest estimate | 2026-10-05 |
| Contract number | 12213202 |

## Why this score
- Contract over $10M.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.