# Harper Brothers Construction LLC: TxDOT widen non-freeway contract 90% complete, SH 5, Collin County ($40,342,065, 18 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Harper Brothers Construction LLC |
| Subcontractors | Iron Concrete Construction Company INC (0.22%); Act Saw Cutting & Removal (0.26%); Antigo Construction, INC. (0.12%); Breda Company, INC. (0.74%); Durable Specialties, INC. (7.36%); Fc Traffic Control, INC. (0.39%); Freight Operation Services, LLC, DBA Fos Brokerage Services (2.39%); Marcoms Construction LLC (0.21%); Mica Corporation (7.36%); Reynolds Asphalt & Construction Company (13.49%); Southern Cross Contractors, LLC (0.16%); Striping Technology, L.P. (1.11%); Texas Environmental Control, INC. (1.45%); Williams Road, LLC (0.44%); Paniolo Construction Services, LLC (4.09%); Charro Boring, INC. (0.12%); Texas Environmental Management - San Antonio, INC. (0%); Precision Road Services, LLC (0.2%) |
| Progress | 90.36% complete, 121.98% of time used |
| Amount | $40,342,065 revised (original $39,271,527) |
| Change orders | $198,738 |
| Paid to date | $35,664,504 |
| Work | Widen Non-Freeway |
| Location | SH 5, SH 121 to NORTH OF COLLIN COUNTY OUTER LOOP, Collin County, Dallas District |
| Let / began | 2022-12-02 / 2023-06-12 |
| Latest estimate | 2026-10-05 |
| Contract number | 12223201 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.