# Harper Brothers Construction LLC: TxDOT widen non-freeway contract 55% complete, FM 2551, Collin County ($46,794,473, 15 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Harper Brothers Construction LLC |
| Subcontractors | 1 Priority Environmental Services, LLC (0.09%); Texas Auger Boring LLC (0.19%); Farr Foundation, INC. (0.41%); Mica Corporation (2.55%); Act Saw Cutting & Removal (0.3%); Marcoms Construction LLC (0.12%); Reynolds Asphalt & Construction Company (10.95%); Traffic Highway Maintenance, LLC (0.56%); USA Swppp Inspections, INC. (0.41%); Breda Company, INC. (0.91%); Texop Construction (0.32%); Durable Specialties, INC. (2.55%); Freight Operation Services, LLC, DBA Fos Brokerage Services (1.66%); Driver Pipeline Company, INC. (0.09%); Precision Road Services, LLC (4.13%) |
| Progress | 54.55% complete, 102.16% of time used |
| Amount | $46,794,473 revised (original $46,333,942) |
| Change orders | $158,731 |
| Paid to date | $25,362,620 |
| Work | Widen Non-Freeway |
| Location | FM 2551, FM 2514 to FM 2170, Collin County, Dallas District |
| Let / began | 2023-04-05 / 2023-11-27 |
| Latest estimate | 2026-10-05 |
| Contract number | 4233202 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.