# Harper Brothers Construction LLC: TxDOT widen non-freeway contract 72% complete, FM 2252, Comal County ($48,503,887, 14 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Harper Brothers Construction LLC |
| Subcontractors | A K Fuquay Construction (1.32%); Flasher Equipment Company (1.02%); Hb Farmer Foundation, LLC (3.06%); The Levy Company, INC. (3.21%); Lone Star Paving Company (13.24%); Hermanos Steel, LLC (0.34%); Penhall Company (0.06%); Toro Bravo Construction, LLC (0.13%); C3 Environmental Specialties, LP (0%); C-3 Environmental Specialties, LP (3.64%); Southwest Road & Safety Contractors, LTD. (1.63%); Eggemeyer Land Clearing, LLC (0.11%); Jb Pinnacle Group, LLC (0.75%); Flovera Construction Services, LLC (1.93%) |
| Progress | 72.07% complete, 83.74% of time used |
| Amount | $48,503,887 revised (original $48,503,887) |
| Paid to date | $34,954,430 |
| Work | Widen Non-Freeway |
| Location | FM 2252, BEXAR/COMAL COUNTY LINE to FM 3009, Comal County, San Antonio District |
| Let / began | 2023-05-04 / 2024-01-29 |
| Latest estimate | 2026-10-05 |
| Contract number | 5233006 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.