# Harper Brothers Construction LLC: TxDOT bridge replacement contract 93% complete, IH 35, Travis County ($36,150,895, 19 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Harper Brothers Construction LLC |
| Subcontractors | Penhall Company (0.1%); Oscar Orduno, INC. (2.54%); Buyers Barricades Austin, LLC (0.12%); Scott Derr Painting Co, LLC (0%); Lawley Contracting, LLC (0%); Environmental Safety Services, INC. (0%); J. R. (Joe) Ramon & Sons, INC. (1.42%); Texas Environmental Management - San Antonio, INC. (1.57%); Toro Bravo Construction, LLC (3.6%); Flasher Equipment Company (1.06%); The Levy Company, INC. (9.1%); Texas Materials Group, INC. (9.5%); Panther Creek Transportation, INC. (2.18%); Primate Construction, LP (0.02%); Hb Farmer Foundation, LLC (8.63%); Royal Rebar INC (0%); Aptus Utilities LLC (0%); Aaron Concrete Contractors, LLC (0%); Emery Sapp & Son's INC. (0%) |
| Progress | 93.41% complete, 126.02% of time used |
| Amount | $36,150,895 revised (original $34,430,611) |
| Change orders | $790,366 |
| Paid to date | $32,899,371 |
| Work | Bridge Replacement |
| Location | IH 35, AT MLK JR. BLVD ON WEST SIDE IH-35 to AT MLK JR. BLVD ON EAST SIDE IH-35, Travis County, Austin District |
| Let / began | 2024-05-02 / 2024-10-07 |
| Latest estimate | 2026-10-05 |
| Contract number | 5243005 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.