# Harper Brothers Construction LLC: TxDOT bridge replacement contract 100%+ complete, FM 455, Collin County ($9,794,600, 14 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Harper Brothers Construction LLC |
| Subcontractors | Texas Environmental Management - San Antonio, INC. (3.88%); Dustrol, INC. (0.96%); Traffic Highway Maintenance, LLC (1.8%); Fc Traffic Control, INC. (0.32%); Southern Cross Contractors, LLC (3.22%); Toro Bravo Construction, LLC (0.85%); Wylie Drilling & Drainage, INC. (5.55%); A. E. Moore Construction, INC. (1.35%); Reynolds Asphalt & Construction Company (12.17%); Dfw Rebar, INC. (0%); West Texas Rumble Strip LLC (0.1%); Stripe-A-Zone, LLC (1.46%); 1 Priority Environmental Services, LLC (0.18%); Paniolo Construction Services, LLC (0.63%) |
| Progress | 100.43% complete, 116.72% of time used |
| Amount | $9,794,600 revised (original $9,581,000) |
| Paid to date | $9,622,633 |
| Work | Bridge Replacement |
| Location | FM 455, AT EAST FORK TRINITY RIVER RELIEF W to AT EAST FORK TRINITY RIVER EAST, Collin County, Dallas District |
| Let / began | 2024-07-10 / 2025-03-13 |
| Latest estimate | 2026-10-05 |
| Contract number | 7243207 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.