# Highway 19 Construction LLC: TxDOT hazard elimination & safety contract 89% complete, US 82, Lamar County ($2,759,026, 2 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Highway 19 Construction LLC |
| Subcontractors | Diamond Elite Barricades, LLC (1.31%); A. E. Moore Construction, INC. (1.71%) |
| Progress | 89.07% complete, 97.38% of time used |
| Amount | $2,759,026 revised (original $2,609,126) |
| Change orders | $67,970 |
| Paid to date | $2,384,428 |
| Work | Hazard Elimination & Safety |
| Location | US 82, US 82 FROM LOOP 286 TO BOWIE COUNTY LINE, Lamar County, Paris District |
| Let / began | 2023-10-05 / 2024-02-21 |
| Latest estimate | 2026-10-05 |
| Contract number | 10233019 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.