# Highway 19 Construction LLC: TxDOT bridge replacement contract 55% complete, CR, Grayson County ($2,824,679, 4 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Highway 19 Construction LLC |
| Subcontractors | Striping Technology, L.P. (0.5%); Southern Cross Contractors, LLC (4.64%); Peachtree Construction, LTD. (5.9%); Diamond Elite Barricades, LLC (0.89%) |
| Progress | 55.38% complete, 47.84% of time used |
| Amount | $2,824,679 revised (original $2,742,958) |
| Paid to date | $1,518,997 |
| Work | Bridge Replacement |
| Location | CR, VARIOUS, Grayson County, Paris District |
| Let / began | 2025-10-09 / 2026-02-18 |
| Latest estimate | 2026-10-05 |
| Contract number | 10253222 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.