# Highway 19 Construction LLC: TxDOT rehabilitation of existing road contract 97% complete, FM 274, Fannin County ($21,005,845, 9 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Highway 19 Construction LLC |
| Subcontractors | A. K. Gillis & Sons, LLC (0%); Richard Drake Construction Company, L.P. (19.63%); Diamond Elite Barricades, LLC (0.16%); A. E. Moore Construction, INC. (1.11%); Striping Technology, L.P. (1.07%); West Texas Rock Resources, LLC (0.08%); Withers Construction, LLC (2.13%); Emery Sapp & Son's INC. (0.02%); Penhall Company (0.04%) |
| Progress | 97.21% complete, 127.6% of time used |
| Amount | $21,005,845 revised (original $19,819,267) |
| Change orders | $300,000 |
| Paid to date | $19,557,603 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 274, FM 274 FROM FM 1753 TO SH 78, Fannin County, Paris District |
| Let / began | 2023-11-01 / 2024-03-18 |
| Latest estimate | 2026-10-05 |
| Contract number | 11233012 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.