# Highway 19 Construction LLC: TxDOT interchange (new or reconstructed) contract 1% complete, US 67, Ellis County ($64,577,574, 8 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | Highway 19 Construction LLC |
| Subcontractors | Reynolds Asphalt & Construction Company (9.49%); Urban Infrastructure LLC (2.67%); Fc Traffic Control, INC. (0.1%); Linear Traffic Markings LLC (0.46%); Act Saw Cutting & Removal (0.25%); Professional Traffic Control LLC (0.06%); Wylie Drilling & Drainage, INC. (0.75%); A. E. Moore Construction, INC. (2.41%) |
| Progress | 0.69% complete, 7.53% of time used |
| Amount | $64,577,574 revised (original $63,703,074) |
| Paid to date | $439,159 |
| Work | Interchange (New Or Reconstructed) |
| Location | US 67, AT LAKE RIDGE PKWY to ., Ellis County, Dallas District |
| Let / began | 2026-03-04 / 2026-07-13 |
| Latest estimate | 2026-10-05 |
| Contract number | 3263002 |

## Why this score
- Contract over $10M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.