# Highway 19 Construction LLC: TxDOT bridge replacement contract 100%+ complete, FM 2658, Rusk County ($9,639,028, 8 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Highway 19 Construction LLC |
| Subcontractors | A. E. Moore Construction, INC. (2.92%); Reynolds & Kay, LTD. (5.81%); Tex Op Construction, LP (0.13%); Flex Supply, LLC (0.13%); Striping Technology, L.P. (1.64%); Scott Derr Painting Co, LLC (0.28%); Je Casey, LLC (2.94%); Penhall Company (0.04%) |
| Progress | 107.37% complete, 144.55% of time used |
| Amount | $9,639,028 revised (original $9,612,238) |
| Paid to date | $10,320,393 |
| Work | Bridge Replacement |
| Location | FM 2658, FM 2658 to BRIDGE REPLACEMENT, Rusk County, Tyler District |
| Let / began | 2023-08-02 / 2024-03-19 |
| Latest estimate | 2026-10-02 |
| Contract number | 8233009 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.