# Highway 19 Construction LLC: TxDOT hazard elimination & safety contract 100%+ complete, US 69, Cherokee County ($4,367,459, 4 subs)

**Score:** 60/100

| Field | Value |
|---|---|
| Prime contractor | Highway 19 Construction LLC |
| Subcontractors | Striping Technology, L.P. (0%); Diibs Specialists, LLC (0.7%); Flex Supply, LLC (0.24%); A. E. Moore Construction, INC. (6.69%) |
| Progress | 105.1% complete, 142.27% of time used |
| Amount | $4,367,459 revised (original $3,673,344) |
| Change orders | $669,115 |
| Paid to date | $4,563,895 |
| Work | Hazard Elimination & Safety |
| Location | US 69, FM 241 to 1.11 MI N OF FM 851, Cherokee County, Tyler District |
| Let / began | 2023-08-02 / 2024-03-04 |
| Latest estimate | 2026-10-02 |
| Contract number | 8233020 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.