# Highway 19 Construction LLC: TxDOT rehabilitation of existing road contract 100%+ complete, SH 19, Hopkins County ($21,297,164, 10 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | Highway 19 Construction LLC |
| Subcontractors | Surface Preparation Technologies, LLC (0.1%); A. K. Gillis & Sons, LLC (14.17%); Diamond Elite Barricades, LLC (0.19%); A. E. Moore Construction, INC. (1.17%); Marcoms Construction LLC (0.54%); Catocon, INC. (1.96%); Richard Drake Construction Company, L.P. (35.83%); Southern Cross Contractors, LLC (0.87%); Striping Technology, L.P. (0.96%); Tex Op Construction, LP (0.17%) |
| Progress | 101.14% complete, 100% of time used |
| Amount | $21,297,164 revised (original $16,786,586) |
| Change orders | $3,633,949 |
| Paid to date | $20,652,531 |
| Work | Rehabilitation Of Existing Road |
| Location | SH 19, SH 19 FROM SH 11 TO RAINS COUNTY LINE, Hopkins County, Paris District |
| Let / began | 2023-08-03 / 2024-01-10 |
| Latest estimate | 2026-10-05 |
| Contract number | 8233214 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.