# Highway 19 Construction LLC: TxDOT hazard elimination & safety contract 92% complete, SH 78, Fannin County ($2,512,349, 5 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Highway 19 Construction LLC |
| Subcontractors | Withers Construction, LLC (6.15%); Southern Cross Contractors, LLC (9.33%); A. E. Moore Construction, INC. (2.39%); Flex Supply, LLC (1.17%); Traffic Highway Maintenance, LLC (1.01%) |
| Progress | 92.14% complete, 120.42% of time used |
| Amount | $2,512,349 revised (original $2,680,198) |
| Change orders | $-242,606 |
| Paid to date | $2,245,945 |
| Work | Hazard Elimination & Safety |
| Location | SH 78, SH 78 FROM US 82 TO OKLAHOMA STATE LINE, Fannin County, Paris District |
| Let / began | 2023-08-03 / 2023-10-09 |
| Latest estimate | 2026-10-05 |
| Contract number | 8233250 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.