# Highway Barricades And Services, LLC: TxDOT hazard elimination & safety contract 82% complete, SH 238, Calhoun County ($1,937,681)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Highway Barricades And Services, LLC |
| Progress | 82.27% complete, 76% of time used |
| Amount | $1,937,681 revised (original $1,886,658) |
| Paid to date | $1,552,161 |
| Work | Hazard Elimination & Safety |
| Location | SH 238, SH 35 to 0.50 MI S OF SH 35, Calhoun County, Yoakum District |
| Let / began | 2025-11-05 / 2026-06-22 |
| Latest estimate | 2026-10-05 |
| Contract number | 11253029 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.