# Hodges And Son Construction Company, INC.: TxDOT bridge replacement contract 99% complete, CS, Clay County ($1,162,246, 3 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Hodges And Son Construction Company, INC. |
| Subcontractors | Morris County Contractors, L.L.C. (4.17%); Wolfe Construction Group, Incorporated (0.23%); Toro Bravo Construction, LLC (0.7%) |
| Progress | 98.67% complete, 83.22% of time used |
| Amount | $1,162,246 revised (original $1,149,814) |
| Paid to date | $1,134,522 |
| Work | Bridge Replacement |
| Location | CS, HANCOCK ST to AT DRY FORK LITTLE WICHITA RIVER, Clay County, Wichita Falls District |
| Let / began | 2025-10-08 |
| Latest estimate | 2026-10-02 |
| Contract number | 10253030 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.