# Hodges And Son Construction Company, INC.: TxDOT bridge replacement contract 99% complete, US 287, Donley County ($4,461,300, 5 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Hodges And Son Construction Company, INC. |
| Subcontractors | Insituform Technologies, LLC (1.01%); USA Amtech, INC. (5.18%); Fc Traffic Control, INC. (0.48%); Morris County Contractors, L.L.C. (0.34%); Trp Construction Group, LLC (1.83%) |
| Progress | 98.88% complete, 93.68% of time used |
| Amount | $4,461,300 revised (original $4,458,100) |
| Change orders | $3,200 |
| Paid to date | $4,411,495 |
| Work | Bridge Replacement |
| Location | US 287, US 287 @ DRAINAGE DITCH to ., Donley County, Childress District |
| Let / began | 2025-02-07 / 2025-05-28 |
| Latest estimate | 2026-10-05 |
| Contract number | 2253215 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.