# Hunter Industries, LTD.: TxDOT bridge replacement contract 61% complete, US 59, Goliad County ($32,213,598, 15 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Hunter Industries, LTD. |
| Subcontractors | A.Z. Rebar Construction, INC. (0%); Sk Concrete Services LLC (0.05%); Southwest Road & Safety Contractors, LTD. (0.85%); Texas Environmental Management - San Antonio, INC. (0.88%); A. H. Beck Foundation Co., INC. (6.09%); Toro Bravo Construction, LLC (0.34%); Jb Pinnacle Group, LLC (1.03%); Lindamood, INC. (0.97%); Farr Foundation, INC. (2.22%); Highway Barricades And Services, LLC (0.3%); 4e Tree Worx LLC (0.17%); Bird Solutions International LLC (0.35%); Jadan Enterprises, LLC (0.42%); Choctaw Erectors, INC. (3.73%); Cnd Contracting, LLC (0.08%) |
| Progress | 61.1% complete, 49.57% of time used |
| Amount | $32,213,598 revised (original $31,574,353) |
| Change orders | $639,245 |
| Paid to date | $19,684,023 |
| Work | Bridge Replacement |
| Location | US 59, ON US59 AT SAN ANTONIO RIVER STR.9 to 3.0 MI. SW OF US 183, Goliad County, Corpus Christi District |
| Let / began | 2024-10-01 / 2025-04-21 |
| Latest estimate | 2026-10-02 |
| Contract number | 10243008 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.