# Hunter Industries, LTD.: TxDOT rehabilitation of existing road contract 8% complete, FM 331, Austin County ($10,762,395, 3 subs)

**Score:** 75/100

| Field | Value |
|---|---|
| Prime contractor | Hunter Industries, LTD. |
| Subcontractors | Texas Environmental Management - San Antonio, INC. (1.26%); Linear Traffic Markings LLC (3.15%); Interstate Barricades & Markings, INC. (0.71%) |
| Progress | 7.83% complete, 6.26% of time used |
| Amount | $10,762,395 revised (original $10,744,493) |
| Paid to date | $841,293 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 331, FM 529 to SH 36, Austin County, Yoakum District |
| Let / began | 2025-12-02 / 2026-05-04 |
| Latest estimate | 2026-10-05 |
| Contract number | 12253016 |

## Why this score
- Contract over $10M.
- Under 25% complete: most materials and sub work still ahead.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.