# Hunter Industries, LTD.: TxDOT bridge replacement contract 94% complete, FM 1115, Fayette County ($1,387,583, 11 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Hunter Industries, LTD. |
| Subcontractors | Jb Pinnacle Group, LLC (2.15%); Rucoba & Maya Construction, LLC (2.4%); Diibs Specialists, LLC (2.11%); Environmental Safety Services, INC. (16.33%); Hermanos Steel, LLC (0.72%); Traffic Signs & Lines, LLC (0.78%); 4e Tree Worx LLC (2.25%); Skyline Bridge LLC (7.09%); Clear Restoration, LLC (1.27%); Houston Sawing & Drilling (0.31%); J. R. (Joe) Ramon & Sons, INC. (2%) |
| Progress | 94.42% complete, 54.17% of time used |
| Amount | $1,387,583 revised (original $1,375,081) |
| Paid to date | $1,298,300 |
| Work | Bridge Replacement |
| Location | FM 1115, AT PEACH CREEK to STR# 1262-01-003, Fayette County, Yoakum District |
| Let / began | 2025-12-03 / 2026-05-05 |
| Latest estimate | 2026-10-05 |
| Contract number | 12253219 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.