# Hunter Industries, LTD.: TxDOT widen non-freeway contract 83% complete, US 77, Fayette County ($118,099,325, 15 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Hunter Industries, LTD. |
| Subcontractors | Toro Bravo Construction, LLC (0.06%); Murray Construction (0.18%); Texas Environmental Management - San Antonio, INC. (0.59%); Professional Traffic Control LLC (0.02%); Hermanos Steel, LLC (0.14%); Sk Concrete Services LLC (0.03%); Eggemeyer Land Clearing, LLC (0.93%); Scr Civil Construction, LLC (1.73%); Creacom, INC. (0.73%); Cnd Contracting, LLC (0.17%); Ats Drilling, INC. (2.21%); Ancortex, INC. (0.4%); Aaron Concrete Contractors, LLC (0.24%); Trp Construction Group, LLC (1.38%); 1 Priority Environmental Services, LLC (0.02%) |
| Progress | 82.92% complete, 107.45% of time used |
| Amount | $118,099,325 revised (original $112,692,666) |
| Change orders | $2,473,653 |
| Paid to date | $95,492,482 |
| Work | Widen Non-Freeway |
| Location | US 77, SH 71 to 0.56 MI NORTH OF CR 156, Fayette County, Yoakum District |
| Let / began | 2024-01-05 / 2024-06-04 |
| Latest estimate | 2026-10-05 |
| Contract number | 1243201 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.