# Hunter Industries, LTD.: TxDOT rehabilitation of existing road contract 67% complete, SH 123, Wilson County ($39,854,993, 8 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Hunter Industries, LTD. |
| Subcontractors | Titan Milling INC. (0.12%); Interstate Concrete & Steel Services Incorporated (7.54%); Murray Construction (0.26%); Professional Traffic Control LLC (0.06%); Trp Construction Group, LLC (1.92%); Eggemeyer Land Clearing, LLC (0.14%); The Levy Company, INC. (0.04%); 4e Tree Worx LLC (0.03%) |
| Progress | 67.21% complete, 82.09% of time used |
| Amount | $39,854,993 revised (original $39,483,858) |
| Change orders | $371,135 |
| Paid to date | $26,786,936 |
| Work | Rehabilitation Of Existing Road |
| Location | SH 123, GUADALUPE/WILSON COUNTY LINE to BS 87, Wilson County, San Antonio District |
| Let / began | 2024-01-05 / 2024-04-01 |
| Latest estimate | 2026-10-05 |
| Contract number | 1243203 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.