# Hunter Industries, LTD.: TxDOT rehabilitation of existing road contract 68% complete, FM 140, Frio County ($14,824,127, 8 subs)

**Score:** 55/100

| Field | Value |
|---|---|
| Prime contractor | Hunter Industries, LTD. |
| Subcontractors | 4e Tree Worx LLC (0.28%); Greyco Construction, LLC (6.17%); Highway Barricades And Services, LLC (0.5%); The Levy Company, LLC (0.09%); Mpb, INC. (0.08%); Professional Traffic Control LLC (0.13%); (Inactive)stripe It Up, LLC (0.41%); Trp Construction Group, LLC (2.28%) |
| Progress | 68.26% complete, 55.29% of time used |
| Amount | $14,824,127 revised (original $14,824,127) |
| Paid to date | $10,119,306 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 140, US 57 to IH 35, Frio County, San Antonio District |
| Let / began | 2025-02-06 / 2025-06-09 |
| Latest estimate | 2026-10-05 |
| Contract number | 2253003 |

## Why this score
- Contract over $10M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.