# Hunter Industries, LTD.: TxDOT widen non-freeway contract 100%+ complete, SH 71, Burnet County ($7,244,972, 8 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Hunter Industries, LTD. |
| Subcontractors | Mg Drilling Foundation, LLC (0%); E-Z Bel Construction, LLC (5.07%); 4e Tree Worx LLC (0.42%); Santa Fe Concrete Services LLC (6.31%); Trp Construction Group, LLC (2.22%); Gbc General Barricade Company LLC (0.36%); Lawley Contracting, LLC (0%); Mpb, INC. (0.12%) |
| Progress | 102.66% complete, 95.14% of time used |
| Amount | $7,244,972 revised (original $7,072,728) |
| Change orders | $74,293 |
| Paid to date | $7,337,314 |
| Work | Widen Non-Freeway |
| Location | SH 71, 0.75 MI W OF CR 401 to 0.75 MI E OF CR 401, Burnet County, Austin District |
| Let / began | 2025-02-06 / 2025-05-01 |
| Latest estimate | 2026-10-05 |
| Contract number | 2253012 |

## Why this score
- Contract over $1M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.