# Hunter Industries, LTD.: TxDOT hazard elimination & safety contract 88% complete, RM 32, Comal County ($3,398,473, 6 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Hunter Industries, LTD. |
| Subcontractors | The Levy Company, LLC (0.19%); Mpb, INC. (27.16%); Trp Construction Group, LLC (5.05%); A K Fuquay Construction (4.72%); Environmental Safety Services, INC. (1.12%); 4e Tree Worx LLC (2.85%) |
| Progress | 87.99% complete, 94.32% of time used |
| Amount | $3,398,473 revised (original $3,391,550) |
| Change orders | $-1,077 |
| Paid to date | $2,983,373 |
| Work | Hazard Elimination & Safety |
| Location | RM 32, RM 484 to 1.95 MI E OF RM 484, Comal County, San Antonio District |
| Let / began | 2025-03-04 / 2025-07-17 |
| Latest estimate | 2026-10-05 |
| Contract number | 3253023 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.