# Hunter Industries, LTD.: TxDOT rehabilitation of existing road contract 53% complete, FM 530, Lavaca County ($5,949,970, 3 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Hunter Industries, LTD. |
| Subcontractors | Stripe Lines, INC. (3.52%); Southwest Road & Safety Contractors, LTD. (0.74%); 4e Tree Worx LLC (0.86%) |
| Progress | 52.94% complete, 81.95% of time used |
| Amount | $5,949,970 revised (original $5,948,468) |
| Paid to date | $3,148,863 |
| Work | Rehabilitation Of Existing Road |
| Location | FM 530, 3.066 MILES SOUTH OF FM 2616 to CR 124, Lavaca County, Yoakum District |
| Let / began | 2025-03-05 / 2025-11-17 |
| Latest estimate | 2026-10-05 |
| Contract number | 3253213 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.