# Hunter Industries, LTD.: TxDOT overlay contract 78% complete, US 59, Live Oak County ($5,338,027, 6 subs)

**Score:** 40/100

| Field | Value |
|---|---|
| Prime contractor | Hunter Industries, LTD. |
| Subcontractors | 4e Tree Worx LLC (1.78%); Clear Restoration, LLC (0.2%); Highway Barricades And Services, LLC (0.57%); (Inactive)stripe It Up, LLC (3.68%); Diibs Specialists, LLC (10.12%); Mpb, INC. (0.22%) |
| Progress | 77.65% complete, 45.14% of time used |
| Amount | $5,338,027 revised (original $5,311,274) |
| Change orders | $26,753 |
| Paid to date | $4,145,128 |
| Work | Overlay |
| Location | US 59, FM 1359 to MCMULLEN COUNTY LINE, Live Oak County, Corpus Christi District |
| Let / began | 2026-03-04 / 2026-06-24 |
| Latest estimate | 2026-10-02 |
| Contract number | 3263010 |

## Why this score
- Contract over $1M.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.