# Hunter Industries, LTD.: TxDOT maintenance contract 55% complete, FM0626, Karnes County ($4,480,606, 2 subs)

**Score:** 50/100

| Field | Value |
|---|---|
| Prime contractor | Hunter Industries, LTD. |
| Subcontractors | A K Fuquay Construction (0.37%); Highway Barricades And Services, LLC (1.39%) |
| Progress | 55.44% complete, 54.11% of time used |
| Amount | $4,480,606 revised (original $1,289,866) |
| Change orders | $3,189,740 |
| Paid to date | $2,483,356 |
| Work | Maintenance |
| Location | FM0626, FM0626 to FM3191 ETC., Karnes County, Corpus Christi District |
| Let / began | 2025-04-03 / 2025-08-01 |
| Latest estimate | 2026-10-03 |
| Contract number | 4254005 |

## Why this score
- Contract over $1M.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.