# Hunter Industries, LTD.: TxDOT overlay contract 100%+ complete, IH 37, Live Oak County ($13,872,538, 6 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Hunter Industries, LTD. |
| Subcontractors | D&G Energy Corporation (1.89%); Highway Barricades And Services, LLC (4.08%); Professional Traffic Control LLC (0.11%); Interstate Barricades & Markings, INC. (0.17%); Texas Cutting & Coring Gp, INC. (0.23%); Scr Civil Construction, LLC (1.1%) |
| Progress | 104.73% complete, 105.83% of time used |
| Amount | $13,872,538 revised (original $13,060,729) |
| Change orders | $811,809 |
| Paid to date | $14,528,340 |
| Work | Overlay |
| Location | IH 37, 0.5 MILES NORTH OF US 59 to SAN PATRICIO COUNTY LINE, Live Oak County, Corpus Christi District |
| Let / began | 2024-05-02 / 2024-08-06 |
| Latest estimate | 2026-10-02 |
| Contract number | 5243010 |

## Why this score
- Contract over $10M.
- Closing out: the prime is bidding its next job.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-11-04T21:51:15.012Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.