# Hunter Industries, LTD.: TxDOT widen non-freeway contract 90% complete, FM 1103, Comal County ($48,887,926, 24 subs)

**Score:** 65/100

| Field | Value |
|---|---|
| Prime contractor | Hunter Industries, LTD. |
| Subcontractors | Adcock 4 Investments, LLC (5.86%); Cox Commercial Construction LLC (5.54%); Fibertel, LLC (0%); Alamo Crane Service, INC. (0%); G 6 Construction, INC. (1.63%); Geosource, INC. (0.08%); Keller North America, INC. (1.36%); Presidio Contracting, LLC (0.75%); Roadway Specialties, INC. (0.29%); S & S Bridge Painting, INC. (0.59%); Trp Construction Group, LLC (0.87%); Texas Environmental Management - San Antonio, INC. (2.55%); E-Z Bel Construction, LLC (4.22%); Frank Jr Reinforcement LLC (0%); C&M Concrete (0%); Aaron Concrete Contractors, LLC (15.58%); A. H. Beck Foundation Co., INC. (2.45%); Environmental Safety Services, INC. (0.06%); Greyco Construction, LLC (2.63%); King Kong Concrete Co LLC (1.38%); 4e Tree Worx LLC (0.04%); C&M Precast Concrete Company (0.96%); Austin Formula Utilities, Limited Liability Company (1.48%); Lone Star Sitework, LLC (3.81%) |
| Progress | 89.51% complete, 30.51% of time used |
| Amount | $48,887,926 revised (original $39,295,624) |
| Change orders | $9,591,302 |
| Paid to date | $43,757,153 |
| Work | Widen Non-Freeway |
| Location | FM 1103, IH 35 to GUADALUPE C/L, Comal County, San Antonio District |
| Let / began | 2021-06-04 / 2022-11-01 |
| Latest estimate | 2026-10-05 |
| Contract number | 6213203 |

## Why this score
- Contract over $10M.
- Change orders 10%+ of the original amount.

Source: Texas Department of Transportation construction contract recapitulation (data.texas.gov) (https://data.texas.gov/d/h3h6-qwdh). Last refreshed: 2026-10-28T20:50:31.263Z.
From TxDOT construction contract recapitulation data, built from monthly pay estimates. Percentages and amounts are as of the latest approved estimate and can lag the field. Subcontractor shares are TxDOT's approved percentages. No TxDOT staff names are included. Verify with TxDOT.